Water Proofing
Water proofing on terrace in 1:3 lime sand mortar
laid to slope. The mortar is left to mature for a period of two weeks subsequent to
grinding and traditional additives like 'gur' and 'saras' water before laying.
Laying of Lime Mortar
Screed on Terrace
 |
 |
| Chipping of the top lime mortar layer |
Filling of cracks and fissures |
 |
 |
| Laying of lime mortar bed |
Reworking with lime water |
|